Short of a complete tear-down and rebuild, jacking up a house is the most extreme measure you can take to alter a house. Jacking up a house is the first step before fixing the foundation or moving the house to another location.
Warning
This is an explainer, not a how-to guide. Lifting an entire house or part of it should not be attempted, both for the safety of yourself and of your house.
Reasons For Jacking up a House
- Foundation repair: Repair or rebuild the foundation wall
- Moving: Relocate or rotate the house
- Repairing: Jacking up part of the house to repair sloping floors
- Floodplain elevation: Lift the house to build or extend the foundation when the house is in a floodplain.
How to Jack up a House
-
Obtain Permits
Apply for permits to lift the house from your local permitting agency. Permits can run between $1,000 and $5,000.
-
Detach Utilities
Detach the house from all utilities and mechanicals such as electricity, sewer, water, and gas. Within the house, secure all loose items.
-
Dig Holes
Holes are created in the foundation for the steel lifting beams. For masonry foundations, concrete blocks or bricks are removed to create holes.
-
Insert Lower Beams
Steel beams are inserted through the holes. The beams run perpendicular to the house's own beams or joists.
-
Add Perpendicular Beams
The second set of steel beams is inserted perpendicular to and underneath the first set.
-
Insert the Jacks
Screw jacks are placed under the steel beams. Supports are placed under the screw jacks to prevent them from sinking into soft ground. Because hydraulic jacks lose pressure, screw jacks are used for house jacking.
-
Raise the Jacks
The jacks are raised about 1/8- to 1/4-inch. As a general rule, a house—including any portion of a house—should be lifted no more than 1/8 inch per day. If you have to raise the house to a total of 1 inch, it will be done in eight or more increments. This slow pace gives all the interconnected materials a chance to settle into the new position without falling apart.
-
Insert the Cribs
Cribs, or wooden supports, are placed under the beams. The cribs are built up in perpendicular stacks.
-
Raise the Jacks on a Continuing Basis
The jacks are slowly screwed upward over a period that usually takes three to four months.
-
Repair the House or Foundation
Make the repairs to the house or its foundation. If a new foundation wall needs to be built, for example, this is built after the house has finally reached its desired height. Proper clearance must be achieved to allow the wall to be built.
-
Lower the House
After the repairs have been made or the foundation has been built, jacking and cribbing are slowly done again, but this time in reverse.
-
Remove the Jacks and Cribbing
After the jacks are free, they are removed, along with all of the cribbing materials.
-
Attach Utilities and Mechanicals
Reattach electricity, plumbing, gas and other utilities and mechanicals. The service drop or buried electrical cables are reattached to the home.
-
How long does it take to jack up a house?
The overall process of jacking up an entire house takes about three to four months. Raising the house can take from one to two months, depending on the size of the house.
-
Can you leave possessions in the house when it's being raised?
Generally, you can keep items in the house rather than moving them out. This is at the discretion of the contractor. Securing a home from theft during house jacking can be difficult since thieves know that the house is unoccupied. So, it's often best to remove valuable items first.